Process description:
The existing roll application process is being converted into a nozzle application process. The applicator rollers are removed and replaced with nozzle bars. For the smooth integration of the new nozzle bars into the existing machine, great emphasis was placed on careful on-site recording in all specialist areas.
The entire conversion was carried out from the beginning of all construction activities to the optimization of the control system in one week.
Tasks:
On-site recording in the DCS area
I&C engineering
Electrical installation supervision
Clarification of process function with METSO
Creating the software on DCS Alcont (Honeywell)
Initial start up, optimization, interface definition and integration of the new functions in the existing logic
Customer staff training